    3. Notifica della pretesa FIDIC entro 28 giorni: la pretesa che si perde prima di discuterla
    Guide & Tutorial

    Notifica della pretesa FIDIC entro 28 giorni: la pretesa che si perde prima di discuterla

    Una pretesa FIDIC può andare persa per la notifica prima di discuterne il merito. Le scadenze del 2017, la posizione degli EAU dopo il Codice civile del 2025 e un registro da copiare.

    1 ottobre 2026
    12 min di lettura
    |
    HAQQ Team
    Notifica della pretesa FIDIC entro 28 giorni: la pretesa che si perde prima di discuterla

    TL;DR: under FIDIC, a claim for time or money can be lost on notice before anyone looks at the merits.

    The 2017 Red Book gives the claiming Party 28 days from awareness to give a Notice of Claim and 84 days from awareness to submit a fully detailed Claim.

    On a GCC project the practical defence is a notice register built at contract award, with AI doing the reading and a named person making every call.

    306 days of delay, and no extension of time

    The East 40 Building in Al Furjan, Dubai, a residential tower of 112 units, was contracted on the FIDIC 1999 Red Book, governed by DIFC law. The DIFC trial judge found that completion was delayed by 325 days, of which only 19 days were due to the contractor and 306 days were attributable to the employer.

    The contractor still did not get its extension of time. The judge held it was debarred by its failure to comply with the time requirements of Sub-Clause 20.1, and he put a figure on what that cost: if it were not debarred, the contractor would be entitled to AED 1,741,313.42 in prolongation damages. On 12 May 2023 the DIFC Court of Appeal dismissed the contractor's appeal.

    The Court of Appeal put it plainly:

    There is no doubt that the 28-day notice requirement in Sub-Clause 20.1 is a condition precedent to the Contractor's entitlement to obtain an extension of time, however strong his claim to an extension of time might be otherwise.

    Delay attributed by the DIFC trial judge in Panther v MESC

    Days of delay to completion, as found by the trial judge (325 in total).

    Employer (Panther)
    306 days
    Contractor (MESC)
    19 days

    Source: Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 016, para. 21. Percentages are our arithmetic on the judge's figures. The contractor's extension of time still failed on notice.

    That is the argument of this post: a construction claim can be lost on paperwork before anyone argues its merits, and the paperwork is a solvable problem. A "condition precedent" is a step you must take before a right exists at all. Miss it and the right does not arise, however good the facts.

    The FIDIC notice of claim clock: 28 days, then 84

    Panther was a 1999-edition contract. FIDIC released the second editions of its Red, Yellow and Silver Books in December 2017, and the 2017 Red Book puts Employer and Contractor claims through the same procedure in Clause 20.

    As Fenwick Elliott summarises it, the claiming Party gives a Notice of Claim as soon as practicable and no later than 28 days after it became aware, or should have become aware, of the event (Sub-Clause 20.2.1). If the Engineer thinks the Notice is late, it must say so, with reasons, within 14 days; if it does not, the Notice is deemed valid (20.2.2). Within 84 days of awareness, or another agreed period, comes the fully detailed Claim: a description of the event, a statement of the contractual and/or other legal basis, the contemporary records relied on, and particulars of the money or time claimed (20.2.4). Claims of continuing effect add monthly interim updates and a final claim within 28 days of the end of the effects (20.2.6).

    Note what the 84 days runs from: FIDIC's own published corrections to the 2017 Red Book confirm it is measured from the date the claiming Party "became aware, or should have become aware of, the event or circumstance", not from the date of the Notice.

    The 2017 Red Book claims clock

    StepTime limitRuns fromIf it is missed
    Notice of Claim (20.2.1)28 daysAwareness of the event (actual or should have)Other Party discharged, subject to 20.2.2 and 20.2.5
    Engineer's late-notice notice (20.2.2)14 daysReceipt of the Notice of ClaimNotice of Claim deemed valid
    Fully detailed Claim (20.2.4)84 days, or as agreedAwareness of the eventNotice lapses if the legal-basis statement is missing
    Engineer's lapse notice (20.2.4)14 daysExpiry of the 84-day limitNotice of Claim deemed valid
    Final claim, continuing effect (20.2.6)28 daysEnd of the effectsCheck your contract

    The 2017 edition is harsher in one place and softer in another. Harsher: under the 1999 edition the detailed claim was due in 42 days, and the Panther Court of Appeal held that missing it was not itself fatal, while under 2017 a missing legal-basis statement can make the Notice lapse. Softer: Sub-Clause 20.2.5 lets the Engineer weigh late submission, including the prejudice to the other Party and evidence of its prior knowledge of the event.

    Read the Particular Conditions before you trust any number above

    FIDIC itself says it increasingly sees "FIDIC contracts" whose General Conditions are substantially rewritten through the Particular Conditions. Its Golden Principles say time periods must be of reasonable duration, and give as a non-compliant example a requirement to notify a claim within 5 days. Al Tamimi & Company wrote in 2015 that Clause 20.1 is often amended to restrict the time periods for notification and to attach time bars to particulars as well. And under the UAE's new Civil Transactions Law, in standard-form contracts "the conditions added to these forms shall prevail over the original conditions, even if the latter are not struck out" (Article 221(3)).

    What a valid notice looks like, and when the clock starts

    The bar for content is low. In Obrascon v Attorney General for Gibraltar, the English Technology and Construction Court said no particular form is called for, and that the notice must describe the event and be "recognisable as a 'claim'". The DIFC Court of Appeal agreed that the 28-day notice "can be short and to the point".

    The bar for form is higher, and it is where good notices die. In Obrascon, a progress report saying "The adverse weather condition (rain) have [sic] affected the works" was "clearly nowhere near a notice". The 2017 forms require a Notice to be identified as a Notice, which, as a 2019 Keating Chambers article puts it, means meeting minutes or progress reports cannot be a Notice unless they are identified as one. Commentary on the second editions adds that Sub-Clause 1.3 names who must sign or send a Notice, and that it goes to the recipient's address in the Contract Data.

    On timing, the courts disagree. Akenhead J in Obrascon reasoned that an extension can be claimed "either when it is clear that there will be delay (a prospective delay) or when the delay has been at least started to be incurred". The DIFC Court of Appeal held instead that the 28 days is "triggered when the Contractor becomes aware (or ought to have become aware) not of the delay or likely delay but of the event or circumstance giving rise to the claim". For a register, the cautious reading is the DIFC one: start the clock at the event, not on the day the delay bites.

    Construction claim time bars in the UAE: the DIFC and onshore differ

    The DIFC has its own contract law, and the Panther contract was governed by it, with disputes reserved to the DIFC Courts. There, the Court of Appeal enforced the 28-day notice and rejected the contractor's good faith argument: the contractor "was a willing party to a contract which included the 28-day notice requirement", and those provisions "admit of no scope for the postulated implied term or obligation of good faith".

    Onshore UAE is less settled, and the statute changed this year. Federal Decree-Law No. 25 of 2025 issued a new Civil Transactions Law, repealed the 1985 Civil Code, and entered into force on 1 June 2026. The new law "shall not apply retroactively to preceding facts and acts, unless the law provides otherwise" (Article 4(1)), so older projects may still be argued under the 1985 text.

    Two provisions carry the argument against strict time bars. Article 443(1) provides that it may not "be agreed that a claim shall not be admissible after a period other than that specified by law". Article 221(1) requires a contract to be performed "in a manner consistent with the requirements of good faith". The commentary we found was written under the 1985 Code, where the same rules sat in Articles 487 and 246.

    On one side, UAE contributors to the IBA's Construction Law International wrote in 2020 that Sub-Clause 20.1 "will not necessarily be treated as a condition precedent to the claim with the effect of precluding recovery as a matter of UAE law", relying on the rule against agreeing a different limitation period. Al Tamimi & Company wrote in 2015 that the Civil Code's good faith, disproportionate harm and unjust enrichment provisions "act against such time bar clauses". On the other side, Fenwick Elliott wrote in 2023 that there is "a common misconception in the UAE" that such provisions will not be enforced, and Hogan Lovells' view was that, on the good faith point, the outcome "should ultimately be the same if UAE law was applied".

    Onshore, then, the position is contested. We did not find a reasoned onshore judgment in English to cite here, and Fenwick Elliott explains why: most UAE construction disputes "are either litigated in the local courts or in arbitration behind closed doors", which makes reasoned English-language judgments hard to find. Our read, for planning purposes: run the project as if every time bar will be enforced, and treat the arguments against it as a fallback for a lawyer to run, not a plan.

    The notices the statute adds (an original count)

    The Civil Transactions Law also carries notice duties of its own. We read all 28 articles of the Muqawala (contracting) chapter of the 2025 law, Articles 812 to 839, in the English text on the UAE government's legislation portal, and searched each for the words "notify", "notice" and "warn" and their variants. Five articles use those words: 816, 818, 825, 828 and 837. In each of the five, whether a notice was given changes who bears a loss or whether a remedy is available.

    Two of them bite the contractor directly:

    • Article 816(3). If defects appear in employer-supplied materials, "or if other factors arose that would hinder the execution of the work in appropriate conditions, the contractor shall immediately notify the employer thereof". If it does not, it is "liable for all consequences resulting from such failure".
    • Article 828(1). On a unit-price bill of quantities, if executing the design needs a non-burdensome excess over the estimated quantities, the contractor must notify the employer and state the expected increase. If it does not, its "right to recover the expenses exceeding the value of the estimated bill of quantities shall lapse".

    Article 816(3) says "immediately"; Article 828(1) states no period. Whether a FIDIC contract displaces them is a question for your lawyer; whether they belong in your register is not.

    Prova HAQQ AI gratis

    Sperimenta la redazione e ricerca legale con IA

    The fix: a notice register, built on day one

    A notice register is two tables. Table A lists every obligation to give notice, once, at contract award. Table B logs every event as it happens and ties it to the obligations it triggers. Copy these.

    Table A: notice obligations (one row per obligation)

    IDSourceTriggerTo, and whereDeadline ruleFormIf missedClause text
    N-01GC 20.2.1, check PCEvent giving rise to a Claim for time or moneyEngineer, address in Contract Data28 days from awareness (actual or should have)Identified as a Notice; describes the eventTime bar, subject to 20.2.2 and 20.2.5Paste verbatim
    N-02GC 20.2.4, check PCSame event as N-01Engineer, address in Contract Data84 days from awareness, or as agreedFully detailed Claim with legal-basis statementNotice of Claim lapses, subject to 20.2.4 and 20.2.5Paste verbatim
    N-03GC 20.2.6, check PCClaim of continuing effectEngineer, address in Contract DataMonthly updates; final 28 days after effects endInterim and final fully detailed ClaimsCheck contractPaste verbatim
    N-04UAE CTL 2025, Art. 816(3)Defects in employer materials, or factors hindering the workEmployerImmediatelyNot statedLiable for all consequencesPaste verbatim
    N-05UAE CTL 2025, Art. 828(1)Unit-price BOQ: design needs excess over estimated quantitiesEmployerNot statedState the expected increaseRight to recover the excess lapsesPaste verbatim

    Table B: event log (one row per event)

    Event IDEvent dateDate awareSource documentRows triggeredDeadlineDays leftNotice sent (ref, date, receipt)Owner
    E-01403 Mar03 MarEngineer's instruction EI-022N-01, N-0231 Mar (N-01), 26 May (N-02)12 (N-01)PendingContracts manager

    E-014 is an illustration, not a real project; its dates count calendar days, so check how your contract defines a day. Two rules make the register work. "Date aware" is a judgement, so a named person signs it off and records why. And the Source column says GC, PC or statute, because FIDIC's own Golden Principles warn that changes recorded only in tender emails, rather than in the Particular Conditions, may lose out to the General Conditions under the contract's priority of documents.

    Where AI fits, and where it does not

    In this workflow AI does the reading and the drafting; the judgement and the sending stay with people.

    • Gather the set first. Contract Agreement, Letter of Acceptance, Particular Conditions and Contract Data, General Conditions, specification, BOQ and programme. A model can only extract obligations from documents it has, which is why intake comes before prompting.
    • Extract Table A, then check it by hand. Ask for every notice obligation with the clause text quoted verbatim, so each row can be checked against the source. A missed row is the expensive error, so a person reads the notice clauses end to end against the output. Why the clause text itself, not a summary, is what you check is its own post.
    • Log each event as it arrives. Add each new letter, instruction or set of minutes and ask which rows in Table A it might trigger. The model proposes; the contracts manager decides the awareness date.
    • Keep the clock outside the model. Deadlines live in Table B and in a shared calendar, reviewed weekly and sorted by days left.
    • Draft, then a human sends. Ask for a Notice of Claim that is identified as a Notice, names the sub-clause and describes the event. An authorised signatory reviews and signs it, it goes by the method in the Contract Data, and the proof of receipt goes in Table B.

    A prompt for step 2:

    text
    You are reviewing the contract documents in this project.
    1. List every obligation on the Contractor to give a notice, Notice or notification, in the General Conditions, the Particular Conditions and any other contract document.
    2. For each, give: clause reference; trigger; deadline and what it runs from; required form; recipient and address for notices; consequence of missing it.
    3. Quote the clause text verbatim.
    4. Where the Particular Conditions change a General Conditions period, show both and say which document prevails under the priority clause.
    5. If a field is not stated in the documents, write "not stated". Do not infer it.

    The numbering is deliberate. HAQQ's own documentation, on multi-part redlining requests, advises numbering them: "Numbered instructions are processed more accurately than paragraph-form requests."

    Doing this in HAQQ today

    The reading and drafting steps above run on features that are live in HAQQ today. Create a project for the contract: files you attach on a project page go into that project's own data room. HAQQ's documentation lists the file types the assistant can read, including PDF, Word, Excel, PowerPoint and CSV, so the BOQ spreadsheet can sit next to the signed PDF. You can upload multiple files for comparative review, ask for a consolidated analysis across a data room, and work in Arabic, English or French.

    For step 5, HAQQ drafts from a prompt or a template, lets you refine the draft with tracked changes, and exports to Word. Nothing in this workflow is automatic: you add each letter to the project as it arrives, and the deadline lives in your register and your calendar.

    This post explains public sources for general information. It is not legal advice, and HAQQ is not a law firm. For a live claim, take advice from a construction lawyer qualified in the law that governs your contract.

    Key Takeaways

    • A FIDIC claim can be lost on notice: in Panther, 306 of 325 days of delay were attributable to the employer, and the contractor's extension of time still failed.
    • FIDIC 2017: Notice of Claim within 28 days of awareness, fully detailed Claim within 84 days of awareness (not of the Notice).
    • Read the Particular Conditions first; amendments often change the periods.
    • In the DIFC the 28-day notice is a condition precedent. Onshore, enforcement is contested; plan as if it will be enforced.
    • The UAE's 2025 Civil Transactions Law adds statutory notices (Articles 816(3) and 828(1)). Put them in the register.
    • Let AI read and draft. Keep the awareness date, the deadline and the decision to send with a named person.

    Sources & further reading

    • Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 016 (12 May 2023), DIFC Courts
    • Obrascon Huarte Lain SA v Her Majesty's Attorney General for Gibraltar [2014] EWHC 1028 (TCC), The National Archives (Find Case Law)
    • Federal Decree-Law No. (25) of 2025 Promulgating the Civil Transactions Law, UAE Legislation portal
    • FIDIC Golden Principles
    • FIDIC, amendments (errata) to the 2017 Red Book
    • Fenwick Elliott, Changes to the Claims provisions in the 2017 FIDIC Red Book (2019)
    • Fenwick Elliott, FIDIC Contracts: time bars, limitation and good faith (2023)
    • Keating Chambers, The Evolution of Notice Provisions in the FIDIC Suite (2019)
    • IBA Construction Law International, FIDIC around the world (December 2020)
    • HAQQ docs, Using the Chat Interface
    • HAQQ docs, AI Document Review
    • HAQQ, AI contract drafting
    H

    HAQQ Team

    Editorial

    Risorse correlate

    AI Contract ReviewAI Contract DraftingLegal AI ChatLegal AI hallucination and fake citations

    Articoli correlati

    La Migliore AI Legale per gli Studi del MENA e di Lingua Araba (2026)

    La Migliore AI Legale per gli Studi del MENA e di Lingua Araba (2026)

    Smetti di scrivere [CLIENTE]: come anonimizzare un documento prima di darlo a un'IA

    Smetti di scrivere [CLIENTE]: come anonimizzare un documento prima di darlo a un'IA

    Software di Contract Lifecycle Management: il Benchmark 2026

    Software di Contract Lifecycle Management: il Benchmark 2026

    Domande frequenti

    What is the time limit for a notice of claim under FIDIC?

    Under both the 1999 and 2017 FIDIC Red Books, the notice is due as soon as practicable and no later than 28 days after the claiming party became aware, or should have become aware, of the event or circumstance giving rise to the claim. The 2017 edition applies the same 28-day rule to Employer claims, which the 1999 edition did not. Check the Particular Conditions first, because amendments often restrict the notification period.

    What happens if a FIDIC 2017 Notice of Claim is late?

    The other Party can be discharged from liability for that event, but through a procedure. The Engineer must give a notice, with reasons, within 14 days of receiving a Notice of Claim it considers late; if it does not, the Notice of Claim is deemed valid. The claiming Party can explain in its fully detailed Claim why the late submission was justified, and the circumstances that may be weighed under Sub-Clause 20.2.5 include prejudice to the other Party and the other Party's prior knowledge of the event.

    When is the FIDIC 2017 fully detailed Claim due, and what must it contain?

    Within 84 days after the claiming Party became aware, or should have become aware, of the event, or another period agreed with the Engineer. The 84 days runs from awareness, not from the Notice of Claim. It must contain a description of the event, a statement of the contractual and/or other legal basis of the Claim, the contemporary records relied on, and detailed particulars of the payment or time claimed. If the legal-basis statement is missing at the deadline, the Notice of Claim is deemed to have lapsed, subject to the Engineer giving notice of that within 14 days.

    When does the 28-day FIDIC notice period start?

    From when the claiming party became aware, or should have become aware, of the event or circumstance. Courts have read that differently. In Obrascon v Attorney General for Gibraltar (2014), the English Technology and Construction Court reasoned that an extension can be claimed when delay is clear or has started. In Panther v MESC (2023), the DIFC Court of Appeal held that the period runs from awareness of the event, not of the delay. For a notice register, the cautious approach is to start the clock at the event.

    Are FIDIC notice time bars enforceable in the UAE?

    In the DIFC, the Court of Appeal held in Panther v MESC (2023) that the 28-day notice in Sub-Clause 20.1 of the 1999 Red Book is a condition precedent to an extension of time. Onshore, the position is contested. The UAE's Civil Transactions Law issued by Federal Decree-Law No. 25 of 2025, in force since 1 June 2026, provides that parties may not agree a claim-admissibility period other than the one specified by law (Article 443(1)) and requires contracts to be performed in good faith (Article 221(1)). Some practitioners argue rules like these can defeat a notice time bar; others expect time bars to be enforced. Plan as if they will be.

    Does a progress report or meeting minute count as a FIDIC notice?

    Under the 2017 forms, not unless it is identified as a Notice: Sub-Clause 1.3 requires a Notice to be identified as one, so minutes and progress reports do not qualify on their own. Under a 1999-edition FIDIC contract (the Yellow Book) in Obrascon, a progress report saying the rain had affected the works was held to be "clearly nowhere near a notice".

    Does UAE law impose construction notice duties outside the contract?

    The 2025 Civil Transactions Law contains some. Article 816(3) requires the contractor to notify the employer immediately of defects in employer-supplied materials or of factors that would hinder the work, failing which it is liable for all consequences. Article 828(1) says that on a unit-price bill of quantities, a contractor who does not notify the employer of a non-burdensome excess over the estimated quantities loses the right to recover that excess. Whether a particular contract displaces these provisions is a question for a lawyer.

    Can AI keep a construction notice register?

    AI can help with the reading: listing every notice obligation in the contract with the clause text quoted verbatim, checking new correspondence against those obligations, and producing a first draft of a notice. The judgement calls should stay with people: the awareness date, the deadline in your calendar, and the decision to sign and send. In HAQQ you can put the contract documents, including PDF, Word and Excel files, in a project's data room, and draft notices from a prompt or template with tracked changes before exporting to Word.

    Cosa c'è dopo?

    Prova HAQQ AI gratis

    Sperimenta la redazione e ricerca legale con IA

    Calcola il tuo ROI

    Scopri quanto tempo e denaro HAQQ risparmia al tuo studio

    Esplora 380+ prompt legali

    Prompt pronti per ogni compito legale

    Torna al Blog

    Articolo precedente

    Perché gli avvocati usano Claude invece dell'IA legale, e dove si inceppa

    Articolo successivo

    Preparalo prima di chiedere: un brief della pratica per il tuo prompt di revisione contrattuale con l'AI

    Indice

    12 min di lettura

    Share this

    Mettilo in pratica

    Fai a HAQQ la domanda che questo articolo ti ha lasciato.

    HAQQ across all devices
    HAQQ Legal AI Platform Logo

    Il tuo Gemello AI Legale e Sistema di Gestione Studio per redigere, fatturare e vincere.

    Scaricalo suApp StoreDisponibile suGoogle Play

    Documentazioni

    • Docs si apre in una nuova scheda
    • Per iniziare si apre in una nuova scheda
    • Sala stampa si apre in una nuova scheda
    • Aggiornamenti del prodotto si apre in una nuova scheda
    • Stato si apre in una nuova scheda
    • Sicurezza
    • FAQ si apre in una nuova scheda
    • Comunità si apre in una nuova scheda
    • Assistenza si apre in una nuova scheda

    Academy

    • Partner si apre in una nuova scheda
    • Corso si apre in una nuova scheda
    • Notizie giuridiche si apre in una nuova scheda
    • Competenze si apre in una nuova scheda
    • Clausole si apre in una nuova scheda
    • Libreria di prompt si apre in una nuova scheda
    • Strumenti si apre in una nuova scheda
    • Hub di ricerca si apre in una nuova scheda
    • Documenti si apre in una nuova scheda

    Sito web

    • eFirm
    • Chat IA Legale
    • App Mobile
    • Motore Justinian
    • HAQQ eBar
    • HAQQ eWallet
    • Prezzi
    • Confrontaci
    • Soluzioni
    • Blog
    • Conosci il team
    • Unisciti a noi si apre in una nuova scheda
    Apri l'app
    • Lingueenarfresitdeptrohi
    • Contattoinfo@haqq.ai
    • Statooperativo·fondato
    • Termini di Servizio
    • Informativa sulla privacy
    • Informativa sui cookie
    • Trattamento Dati
    • Persone si apre in una nuova schedaAvvocati si apre in una nuova schedaSicurezza si apre in una nuova scheda
    © 2026 HAQQ Inc. Tutti i diritti riservati.Prodotto sviluppato internamente da HAQQ. Sito web costruito con strumenti web moderni.